Customer

Biosar is an international renewable energy market company, specialising in constructing photovoltaic plants (solar farms) and connecting them to the grid.

Objective

Biosar were looking to team with a delivery partner to support their expansion of renewable energy in Australia and asked Yurika to harness our experience in HV connection and construction to accelerate the delivery of the Susan River Solar Farm substation.

Solution

Our key deliverable was to design, construct and transfer (DCT) a solar farm substation.  

  • 74 MW delivered capacity
  • Design and construction of 66/33kV substation that could be transferred to the DNSP, Ergon Energy
  • Installation of dead tank, 2000A circuit breaker 66kV
  • 66kV air break switch
  • Installation of 66/33kV 80MVA transformer
  • Installation of 33kV auxiliary and voltage transformers
  • Testing and commissioning 33kV control/ equipment building, including inverter stations.

Outcomes

  • Our design and construction teams incorporated utility-compliant specifications, equipment, and Australian manufactured transformers
  • Delivered within the agreed timeframe and budget
  • Successfully maintaining a 0% the tota; recordable injury frequency rate (TRIFR)
  • Partnered with Biosar to deliver further renewable projects.

Getting this solar farm up and running to meet an accelerated delivery timeframe was a real community effort with local quarries, concrete suppliers, fuel suppliers and local labour significantly contributing to the successful completion of this project.

Interested in these services?

Related reading

Energy & Infrastructure
Solar farms and rooftop systems
EHV, HV & MV infrastructure
Transmission & Distribution
Susan River Solar Farm
Duration
9 months
$ Value approx
$4m
Service
Solar Farm Substation
Location
17km south of Hervey Bay, QLD
Delivered in 9 months
Meet the team

Customer

Biosar is an international renewable energy market company, specialising in constructing photovoltaic plants (solar farms) and connecting them to the grid.

Objective

Biosar were looking to team with a delivery partner to support their expansion of renewable energy in Australia and asked Yurika to harness our experience in HV connection and construction to accelerate the delivery of the Susan River Solar Farm substation.

Solution

Our key deliverable was to design, construct and transfer (DCT) a solar farm substation.  

  • 74 MW delivered capacity
  • Design and construction of 66/33kV substation that could be transferred to the DNSP, Ergon Energy
  • Installation of dead tank, 2000A circuit breaker 66kV
  • 66kV air break switch
  • Installation of 66/33kV 80MVA transformer
  • Installation of 33kV auxiliary and voltage transformers
  • Testing and commissioning 33kV control/ equipment building, including inverter stations.

Outcomes

  • Our design and construction teams incorporated utility-compliant specifications, equipment, and Australian manufactured transformers
  • Delivered within the agreed timeframe and budget
  • Successfully maintaining a 0% the tota; recordable injury frequency rate (TRIFR)
  • Partnered with Biosar to deliver further renewable projects.

Getting this solar farm up and running to meet an accelerated delivery timeframe was a real community effort with local quarries, concrete suppliers, fuel suppliers and local labour significantly contributing to the successful completion of this project.

Interested in these services?

Related reading

Energy & Infrastructure
Solar farms and rooftop systems
EHV, HV & MV infrastructure
Transmission & Distribution
Susan River Solar Farm

Image Credit: Elliot Green Power